Azerbaijan restores energy infrastructure in liberated Kalbajar and Lachin districts


"Azerishig" OJSC continues its reconstructure works in all liberated territories of Azerbaijan, as well as in Kalbajar and Lachin which has the most difficult relief due to its geographical structure, CJSC told.

According to the Company, in the territory of the city of Kalbajar, the construction of a new substation with a capacity of 35/0.4 kW and a Control Center is proceeding at an accelerated pace, and in the territory of Istisu - a substation with a capacity of 110/35 kV.

Large extended works are being done in Lachin too. Currently, electricity grids in Gorchu and Tighik direction are being updated. The laying of underground lines continues in the Lachin district. To supply important facilities that are located in Shelve, Malibeyli, Garagol, Jagazur and Minkand villages of Lachin the construction of 35 kV power transmission lines has been completed.

Overall, at the end of the works that are done a circular electricity supply scheme will be created, connecting the electricity grids of Kalbajar and Lachin regions.

Azərbaycan Ordusunun sentyabrın 27-də işğalçı Ermənistan silahlı qüvvələrinə qarşı başladığı əks-hücum əməliyyatında əldə etdiyi möhtəşəm qələbələr haqqında bundan sonra kitablar yazılacaq, filmlər çəkiləcək. Amma indidən tam əminliklə deyə bilərik ki, cəbhə uğurlarımızın ən başlıca səbəbi Prezident, Ali Baş Komandan İlham Əliyevin həyata keçirdiyi güclü dövlət, güclü ordu strategiyası, milli birlik və döyüşçülərimizin ruh yüksəkliyi idi.